Diagnosing problems in your Manufacturing Planning and Control (MPC) systems and permanently fixing them

Part 2. Planning the improvement, implementing it and making it stick

This second of two articles on permanently solving problems in MPC systems discusses the methods of prioritising the issues arising from the analysis and solving the problems permanently. The symptoms of your problem may have been: Excess inventory, stock obsolescence, on time delivery, supplier performance, assembly shortages, the need to reduce poor lead-times, or shortage of working capital. You should by now know the real underlying reasons, particularly if you have undertaken our two principle training courses on this subject (below).

Links to further best practice articles and training at bottom of page

Back to Part 1 Diagnosing the problems

Planning the Improvement

I hope you have resisted the temptation to dive in and start fixing your 100 or more problems arising from the diagnosis. (See Diagnosing Manufacturing Planning & Control Problems)

 

There are two problems here:

  1. Determining the causes?
  2. How do you sequence the fixes?

Determining the Causes?

Dealing with providing the appropriate solution first. As I said in the first article the solution is often self evident if the analysis is done properly. In particular the root cause of the problem must be sought for each problem, so that the cause (and not the symptom) is being tackled. The "5 why's" and Pareto techniques described in the first article, (Pareto Analysis is further described in Previous Technique of the Week 006: "Pareto Analysis") are particularly valuable in this, as are a number of other problem-solving techniques. Sampling case histories and a post-mortem after a problem is also useful, provided recrimination is not the motivation for doing it. As an example if the diagnosis reveals amongst other things that stock accuracy is inadequate, it obviously needs to be improved by implementing improved facilities, disciplines and procedures. Or if a procedure is missing for example "capacity availability recording", it needs to be implemented.

It is not the purpose of this article to finesse the application of appropriate best practices, but to ensure that all the major building blocks for effective MPC systems are present. Often we find finesse being applied to situations where there are other glaring omissions in other areas that will overwhelm the finesse being attempted (often at great cost). Before any finesse is attempted all the questions in the first article must be answered positively. This issue is particularly relevant to computerisation, where solutions to the wrong problem or over-sophistication are commonplace. Shuffling deck chairs on the Titanic to improve the view, springs to mind at this point. The outcome of this stage is a list of root causes or significant causes.

Often the analysis also reveals the same root cause for a number of symptoms. This will emphasise the need for change in this area. The outcome of this stage is a consolidated list of root causes or significant causes.

How do you sequence the fixes?

We consider a number of factors guided by our experience in this area as follows:

Impact / Ease Analysis (See also Previous Technique of the Week 030: Impact / Ease Analysis)

We use a simple technique by asking two questions:

  1. What is the impact of the problem / fix on the strategic objectives of the business?
  2. How easy is it to fix? ("Ease" can be defined as simple, cheap, quick, or not requiring much resource.) Then we draw a matrix:

Then we populate the matrix with the issues:

Quality / Delivery / Cost Implications

There are basically two approaches here, short-term expediency or lasting long term improvements. Whilst these are not always in conflict they can be. The following arguments may help you to decide:

If you are bleeding to death, stop the bleeding by tackling the high impact / easy to do things, yesterday. (No conflict of priority here.) However if there is a conflict of interests or resources the following could be used as a guide:

Policy / procedures

Policies are usually far reaching, often constraints on the business, but often easier to change than procedures. However the author of the policy (and their reputation) is high in the organisation, so that aspect of the change process must be handled carefully. Examples might include a review of make vs. buy, or make for stock vs. make to order.

Top down / bottom up procedures

Generally it is better to start at the top and work down if there is a conflict of interests or resources, because the top things usually have the most impact and could make some lower level actions unnecessary. For example a detailed shop scheduling system will not work if there is simply insufficient capacity. You will simply be creating a bottleneck and sucking in raw materials for products you do not have the capacity to make. This can be determined by Master Production Scheduling (see Participative Sales and Operations Planning) much more easily and far earlier than detailed shop scheduling which could then be greatly simplified.

Planning / Control

Generally quicker effects can be seen by taking short-term control actions first, before fixing faults in the planning process, as this tends to be easier to implement. As an example: It is relatively easy to reduce WIP and lead-times by progressively restricting the issue of components from raw materials store before the planned start date of the order, until productivity is adversely affected, then back off a little. This technique rarely affects customer delivery performance and often removes scheduling problems completely because there is less WIP to schedule.

Omissions

Omitted processes have a higher priority than all other issues. This is simply because the absence of these will probably cause your other efforts to fail.

Keep it simple stupid (KISS)

Avoid sophistication at all costs until all the processes (however crude) are all in place, and the need for further sophistication has been justified.

Planning Summary

Determine root causes

Consolidate

Prioritise / Sequence

KISS

Act (Implementing the Improvement)

Take the necessary actions to solve the problems. But do the analysis first. Control systems can give misleading symptoms, and you could be doing the wrong thing, or the right thing in the wrong sequence, which could make things (fatally) worse. As I said at the beginning, often the fix is simple provided you have done the analysis and prioritising first. But be very clear and focused:

Making the change stick

So you have solved the problem. Stop congratulating yourself. You have not finished yet!

Adapt

Unfortunately this aspect of the change is often viewed as "Low impact / hard-to-do" using my words, and is often not done because some other crisis diverts management attention, or the champion is seen a saviour and is instantly promoted before the job is finished. But without it, all your previous accomplishments will slowly degenerate and have to be repeated later.

This review should cover:

Now you have completed the cycle below, permanently solved the problem and have finished!

 

________________________________________________

The following further best practice articles were also mentioned in this paper:

Part 1 Diagnosing Problems in Manufacturing Planning & Control Systems

 

Participative Sales and Operations Planning

 

Previous Technique of the Week T006: "Pareto Analysis"

Previous Technique of the Week T030: Impact / Ease Analysis

5 why's

Previous Best Practice of the Week B045: OTIF Measuring On-time delivery

 

 

The following public training courses and in-house workshops provides solutions to diagnosing manufacturing planning and control problems:

SSC04 Production Planning & Control Back To Basics (Includes our unique 180 point self diagnostic health check which you should be able to complete following the course to determine your development needs.)

 

You may also be interested in the following related courses:

S02 Business Process Reengineering (Detail)

S03 Vision of a World Class Organisation

C04: Continuous Improvement Basic Tools & Techniques

M04 Participative Master Production Scheduling

M05 Simple Capacity Planning & Control

M10 Simple Stock Control

M11 Simple Ways to Maximise Output & Workflow

SSC02 Materials Control Process Selection

SSC08 Participative Sales & Operations Planning

OM02 Managing & Improving Individual Skills & Overall Skill Levels

 

______________________________________________________________________

To discuss your consulting or training needs with one of our independent consultants or trainers please Contact Us.

Home Page

Summary: Best Practice Business Processes

Summary: Change and Improvement

Summary: E-commerce, IS / IT

Summary: Training Courses

Your Question

Help

This Week's Features

About SM Thacker & Associates

© SM Thacker & Associates (Consultancy and Training Specialists) April 2000 version 3 August 2007