Capacity Management

This article describes our approach to Capacity Planning and Control encompassing, Goldratt and his "Theory of Constraints", Rough Cut Capacity Planning (RCCP), "Participative Master Production Scheduling (MPS)", Lean Manufacturing and Supply Chains and "Pull" systems. It also discusses how to avoid spending lots of money on Advanced Planning and Scheduling (APS), Work flow, BPM or MRP2 systems, Finite material and capacity planning (including OPT, and PERT networks)

Links to other best practices and training at bottom of page.

There are two components of capacity management:

  1. Capacity Planning (creating sufficient, flexible, capable, capacity & a valid, best, "Do-able", resilient, plan, to accommodate demand)
  2. Capacity Control (ensuring the plan is met by managing resources)

Without capacity (and materials) to meet the demand, the plan cannot be valid.

A. Capacity Planning

There are, in a typical business, four levels where capacity planning (& control) is required as shown below. At each of these levels there may be a one to many relationship with the level below. There are certainly differences in both detail required to satisfy this level and planning horizon, which in the case of strategic planning at level one, product groups are being forecast with an horizon of many years. At level four, when you are managing an individual resource, you are dealing with detailed operating instructions and horizons of seconds:

Taking each of these levels in turn:

  1. Strategic Capacity Management (business planning) includes capacity planning relating to:
  2. Sales and Operations Management (Management of the demand and the gross capacity to meet it) (This is mainly covered in a separate article "Participative Sales and Operations Planning".)(See below.)
  3. Workflow Management / Scheduling (Scheduling of individual cells or process areas)

 

Finite material and capacity planning (including OPT, and Advanced Scheduling Systems, and PERT networks)

There is no doubt that mathematical approaches to scheduling are both valid and precise. You should bear in mind though that you can be precisely wrong!, and there are some practical problems. Businesses are complex, uncertain places. So to be accurate the mathematical models must reflect the complexity and statistical uncertainty of reality. This leads to a number of practical problems.

  1. It requires a specialist to run it.
  2. Potentially very large computer models are required, which are unstable if there is uncertainty e.g. Absenteeism, quality problems, process breakdowns etc.
  3. It is very difficult to understand why the "work to" list says what it says, and the plan is imposed not agreed.
  4. Administration of the data is very high which means:
    1. It is inefficient
    2. It becomes inaccurate very easily

These systems were widely used before the implementation of product-focused processes and Kanban systems, which have proved far simpler and in many cases superior.

"Drag & Drop" electronic loading boards have some utility in resolving scheduling problems where a manual loading board has reached its limits, but they suffer the same disadvantages above.

There are a number of issues relating to the maintenance of valid computer capacity models:

There is a further issue also relating to the documentation of the process, which can become a barrier to change. For example in the pharmaceuticals industry, process control documentation is of paramount importance as a quality assurance and control mechanism. However the documentation of the capacity planning parameters can create significant administration.

You need to take a staged approach to implementing sophisticated scheduling tools of any description. What you need to do is:

These arguments are still valid in the context of infinite capacity plans contained in many MRPII systems. We describe this process in detail in our courses M02 Advanced Scheduling Systems & M23 Capacity Management.

  1. Process Management (E.g. individual settings, speeds, feeds, skills, set / make ready times etc.)

    At level four we have been involved in some interesting & lively debates about:

    We deal with all of these issues in courses M11 Simple Ways to Maximise Output & Workflow & OM02 Managing & Improving Individual Skills & Overall Skill Levels

 

B. Capacity Control

Firstly we believe that the 3 dimensional approach of Overall Equipment Effectiveness (OEE) is inadequate, and the six big losses of OEE incomplete. In fact we have identified 21 so far, each of which needs to be resolved individually. (See Previous Technique of the Week T007: "Equipment effectiveness measurement (Or why OEE / OME is for the birds)")

Secondly much is made of the process of capacity planning and in particular in the availability of sophisticated re-planning tools. A university professor recently stated that all of their post graduate research projects in manufacturing systems engineering were dedicated to seeking the holy grail of the ideal scheduling algorithm. However if as much attention was paid to meeting the plan instead of constantly changing it we think the process would be significantly more productive and also constantly improving.

Thirdly much is also made of "sweating the assets" or "maximising productivity". In fact there is only one asset in your business that needs to be operationally sweated & that is the bottleneck. Often this bottleneck is a service area or sometimes, if the order book is low, the sales department. (See Malpractice M006: Hitting the numbers.) Sweating a non-bottleneck will produce unwanted output! To  illustrate of this point, answer the following question: How much output should operations ideally produce if the order book is empty? The answer of course is zero. So why are operations measured on maximising output? The key question is how can we de-bottleneck, perhaps by reassigning underutilised resources . We have developed a new way of defining resource capability, de-bottlenecking and getting more output from them which we teach in M05 Simple Capacity Planning & Control.

Capacity control operates at all four levels:

  1. Business Planning (where typically budgetary type controls operate)
  2. Sales and Operations / Master Production Schedule, where the overall plan is measured and performance against the plan analysed and actions taken to bring output into line with demand.
  3. Workflow which is typically short term, which can be minutes, hours or days depending on the lead-time, where short term actions are taken to bring the plan and achievement into line
  4. Process Management conformance to requirements. (E.g. Why everyone is not using the same "best" method.)

The difference is really the level in the organisation where the decisions need to be taken, which depends on the impact. This tends to be strategic & long term at business level, but tactical & short term where the horizon also tends to be shorter for local decision making.

The timeliness of control is a key element, which can be illustrated as follows:

In the left hand diagram if action is taken now the deviation can be corrected fairly easily. If the action is taken later the shortfall (in this case) in the right hand diagram has accumulated and recovery is much more difficult. In one case we were involved in, a 28 week recovery plan was needed to remove a 3 week backlog.

There needs to be a mechanism to exercise the control involving the stakeholders. This implies a meetings structure to discuss the issues and to resolve the problems. These may include:

In the case of a food manufacturer with 8-hour customer required lead-times, a meeting was held between the production supervisor and the production planner every hour.

 

Conclusion

You may not be short of capacity. You may be short of a capacity planning process at any any of these four levels. You may also be short of a capacity control process which should ensure that these plans are met, and which does not cause conflicts by employing faulty measurement giving rise to local optimums. For example a local control system which encourages output may simply produce unwanted inventory.

Resources are defined by their Capability, Availability, Reliability, Agility, Timeliness) ("CARAT"). But these are not the only influences on output. A more comprehensive list would include: Specification, Culture, Organisation, Processes / methods, Environment & finally Resources ("SCOPER").

In preference to applying sophistication, you could employ simplicity as a means of improving output & workflow. We recommend the Capacity 4S's (which correspond to the four levels) as the lowest overall cost method of managing capacity:

  1. Segment the process to create (virtual) cells (A virtual cell is made up of a group of (not necessarily co-located) resources designed to deliver a product (family) ideally customer facing and encompassing the whole supply chain (Also see "Organisation Redesign" below)
  2. S&OP (Sales & Operations Planning) to ensure plans are "do-able"
  3. Sequence the work for most efficient bottleneck processing & good workflow
  4. SMED the set-up / make ready between tasks to reduce non productive time on the bottleneck

We cover the key aspects of items two & three & four in M23 Capacity Management, & item one, the formation of virtual cells, SCOPER / CARAT Analysis & the 21 wastes in S02 Business Process Reengineering., & S03 Vision of a "World Class" Organisation.

___________________________________________________________

The following further best practice articles were also mentioned in this paper:

Lean Manufacturing

Lean Supply Chains

Agile Manufacturing

Kanban

Participative Master Production Scheduling

Materials Management and Stock Control

Organisational Redesign

MRP1

MRP2

Capacity exchange curves

 

From our archives:

Previous Technique of the Week T007: "Equipment effectiveness measurement (Or why OEE / OME is for the birds)"

Previous Technique of the Week T017: "Loading Boards" (Simple Scheduling Systems)

Previous Technique of the Week T020: "Close Scheduling"

Previous Technique of the Week T021: "Takt Time"

Previous Technique of the Week T033: "Process FMEA"

Previous Best Practice of the Week B005: "Level Scheduling"

Previous Best Practice of the Week B006: "Scarce Skills Management"

Previous Best Practice of the Week B035: "Out Tray Management"

Previous Best Practice of the Week B045: "OTIF Measuring On-time Delivery"

Best Practice of the Week B046 "Using Takt time to manage your business"

Malpractice M006: "Hitting the numbers"

The following public training courses and in-house workshops cover capacity management:

The following 8 training courses cover best practice capacity management:

Level 1: Business Planning

1.      S04 “Strategic Capacity Management” provides a guide to Business Planning using modern capacity strategy best practice

Level 2: Sales & Operations Planning

2.      M04 "Participative Master Production Scheduling" describes high level capacity planning processes of sales and operations planning, but focused on operations and master production scheduling rather than sales planning (this course is designed in conjunction with M05 below)

3.      M05 "Simple Capacity Planning and Control" describes how to design, implement and operate simple Capacity Planning & Control Systems (this course is designed in conjunction with M04 above)

4.      SSC08 “Participative Sales & Operations Planning” takes an holistic view of both sales planning & operations planning processes in equal part, and applies the principles of capacity management to non-manufacturing & manufacturing businesses

Level 3: Workflow Management / Scheduling

5.      M09 “Manufacturing Resources Planning” describes the MRP2 approach to capacity management (M08 "MRP1" is a prerequisite for this course)

6.      M02 "Advanced Scheduling Systems" describes scheduling theory & APS systems in detail

Level 3/ 4: Simple Scheduling / Process Settings / Speeds / Set Up / Make Ready

7.      M11 “Simple Ways To Maximise Output & Workflow” describes detailed ways of maximising throughput at an operational level

 

Guide to Capacity Management

8.      M23 "Capacity Management" provides a guide to capacity management  for beginners, drawing on key aspects from all of the above capacity planning & control courses

 

Also you may be interested in our range of operations management training including OM02 Managing & Improving Individual Skills & Overall Skill Levels,

or the creation of simple, effective, processes in S02 Business Process Reengineering, or an executive overview of key aspects of world class organisations in S03 Vision of a "World Class" Organisation

 

To discuss your consulting or training needs with one of our independent consultants or trainers please Contact Us.

 Home Page

Summary: Best Practice Business Processes

Summary: Change and Improvement

Summary: E-commerce, IS / IT

Summary: Training Courses

Your Question

Help

This Week's Features

About SM Thacker & Associates

© SM Thacker & Associates (Consultancy and Training Specialists) Version 6 December 2007