Achievable Benchmarks
The following benchmark performances have been achieved for quality, productivity, delivery, agility, purchasing, and production control prerequisites in manufacturing industry. Comparisons are difficult since some industries are inherently better than others for good reasons, however in many cases performance can be improved significantly by following the best practices outlined on this site and the Benchmarking procedures outlined in "Introduction to Benchmarking".
Links to other best practices and training at bottom of page.
|
Measure |
Benchmark (Best we know) |
Calculation |
Our best project |
Where are you? |
| Quality | 25 faults per million produced | Quantity of defects x 106 ¸ Total | 120 | |
| Productivity | 666,000$ per employee pa | Sales ($)¸ number of employees | £120,000 | |
| Production Planning | +/- 2% of planned achievement | Full quantity on the day (Plan verses actual) | 3% | |
| Delivery to customers request | 98% delivered as requested | This is based on the customer's desired date not the agreed date (which may be later) (See Previous Best Practice 045: OTIF (on time in full) | 98% | |
| Demand forecast accuracy | >95% | Accurate quantity and date (based on hits and misses) (See Forecast Accuracy, and Demand Management) | 100%
|
|
| Arrears/overdue sales orders | Zero | Any overdue is a miss | 1% | |
| Capacity Planning | +1, -10% | Planned capacity balanced to required capacity | +5%, -10% | |
| MRP schedule adherence | 99.5% | % of all work orders complete (full quantity on the day) | 97% | |
| Most overdue shop order | <2 days | Past due shop order | 3 days | |
| Pick material Shortages from raw materials | <2% | Over due purchase order quantities (less than full quantity on the day) | <2% | |
| Open purchase and shop order accuracy | >95% | At a stock take all orders are real and accurate counted as either accurate or inaccurate (hits & misses) | 90% | |
| Shop orders started on time | >99% | % of planned orders started on the planned day | 99% | |
| Shop orders completed on time | >98% | % of planned completions | 98% | |
| Engineering data | ||||
| Bill of Material Accuracy | >98% | All single level B.O.M.s are audited at build time and are either completely right or wrong | >98% | |
| Routing Data accuracy | >98% | All planned routes audited against actual and are completely right or wrong | Not available (See note 1) | |
| Engineering Change | >95% on time | All engineering changes implemented to schedule | 85% | |
| Purchasing | ||||
| Raw material availability (No shortages) | 98% on time | Picking or Kanban shortage to production line | 94% | |
| Supplier on time | >95% | Full quantity on the day, with perfect quality | 90% | |
| Overdue purchase orders | < 2 days | Full quantity, perfect quality | Not available (see note 2) | |
| Inventory record accuracy | >95% hits | Bin quantity accurate to 2% (to system) when counted. Within 2% is a hit. Outside 2% is a miss. | 94% | |
| Flexibility | ||||
| Lead-time | < 2 days | Lead-time from order to delivery of complex make to order assembly | 5 days | |
| Changeover time | 7.9 minutes for large press die | End of one batch to set up and make first satisfactory component of new batch | 11 minutes for large complex former | |
| Innovation Ideas raised |
>10 | Ideas raised per person per week. (Not all of these will make it.) | 5 | |
| Ideas implemented | >3 | Ideas implemented per week per person | 2 | |
| Stock Turns | 160 (one and a half days stock) (See note 3) | The ratio of raw material issues to total stock holding at material costs. | 20 (See note 3) | |
| The UK Department of Trade and Industry also recommend the following further measures and they are included for completeness rather than because we believe in them: | ||||
| Overall Equipment Effectiveness | Not available | Availability % x Productivity % x Quality % | We do not use this measure (See note 4) | |
| Floor Space Utilisation | Not available | Sales revenue per square metre of floor space | We do not use this measure (See note 5) |
Note 1: We do not view this as too important for planning and scheduling, or costing, and is only important for routing work in non cellular factories. Although it is often important for specifying the required processing, for quality purposes and product recall. This will be covered in a future article.
Note 2: We tend to use raw material line shortages since this measures overall availability to where the items are needed and includes direct line feed methods and raw material stores efficiency.
Note 3: It is difficult to provide outside industry comparisons for stock turn, except it is possible to quote some examples for particular industries:
| Automotive component manufacturer | 14 is the best we have achieved in high mix situations using MRP techniques alone |
| 160 refers to Kanban in an continuous automotive situation | |
| FMCG's | 20 is the best we have achieved in lower mix situations of assemblies using Kanban techniques. |
| Aerospace | 16 is the best we have achieved in high mix situations using Kanban systems. |
Note 4. We do not recommend the use of Overall Machine Effectiveness OME / OEE (See Previous Technique of the Week 006: RAP (Why OEE / OME is for the birds) because we feel it is meaningless for any resource other than the bottleneck. We also do not recommend composite measures such as this because it does not help in problem solving.
Note 5. In most of our work floor space savings may be an objective. However ongoing measurement is unlikely to influence this. These changes can only be brought about from major change programmes, which might include:
Cellular Manufacturing (See "Organisational Redesign")
Flexibility Changes (See "Agile Manufacturing")
Control systems changes such as Kanban, Participative Sales and Operations Planning etc.
__________________________________________________________
Other articles mentioned in this document include:
|
Participative Sales and Operations Planning Previous Technique of the Week 007: RAP (Why OEE / OME is for the birds Previous Best Practice of the Week 045: OTIF (on time in full) |
__________________________________________________________
To discuss your consulting or training needs with one of our independent consultants or trainers please Contact Us.
|
Summary: Best Practice Business Processes |
© SM Thacker & Associates (Consultancy and Training Specialists) April 2000. Updated Sept 2005
![]()